I. CALL TO ORDER

II. INFORMATION ONLY

A. Notice of Emergency Repairs to the Buckbee Channel located near the corner of Wesleyan Avenue and 25th Street. Previously Konstruction Services had sent a quote and been awarded the job for repairing the same section of channel where the rip rap from a previous repair had washed away. Due to the use of this channel for stormwater conveyance it was determined that the repairs were needed on an emergency basis to ensure public safety and prevent further damage to the channel. The total cost of the repairs was $30,250.00. The funding source is CIP General Fund.

B. Change Order: Rockford Watch Factory Roof to HC Anderson Roofing Co., Inc., of Rockton, Illinois.

Original Contract amount $83,885

Proposed Change Order $35,000

Total Amended Contract $118,885

Dynamic delayed their start work date for the roofing materials until this fall when crews would be available, with an agreed upon start date of October 18, 2021. On October 5, 2021, Dynamic notified the City that their current workload will prevent them from completing the work. Immediately upon removal of the asbestos containing roofing materials, a new roof is needed to stabilize and preserve the Historic Watch Factory building until redevelopment. Installation of the new roof was awarded to HC Anderson Roofing Company, Inc. at the September 20, 2021 City Council meeting in the amount of $83,885. It is critical that removal of the old roof and installation of the new roof be completed as soon as possible. The funding source is USEPA Cleanup Grant with the 20% match will be met by a combination of City Staff time, in-kind services and the East River TIF District, if needed.

III. RESOLUTIONS

A. Award of RFP: IT Services to Dyopath LLC, (Formally Innovative Technology Solutions), of Schaumberg, Illinois in the amount of $1,318,348.08. The contract duration is a two (2) year initial term, with three (3) annual one-year options to renew. The funding source is Information Technology Fund.

B. Award of RFP: Water Division Cost of Service Rate Study to Burns & McDonnell Engineering Co., Inc., of Downers Grove, Illinois for a cost not-to exceed $68,155. The contract duration is one (1) year. The funding source is Water Fund Operating Budget.

C. Award of Non-Competitive Contract: Compound Water Meter Supplies to Core & Main LP, of Belvidere, Illinois for an estimated annual value of $200,000. The contract duration is one (1) year. The funding source is Water Fund Operating Budget.

D. Award of Non-Competitive Contract: Mechanical Water Meter Supplies to Badger Meter, Inc., of Milwaukee, Wisconsin for an estimated annual value of $200,000. The contract duration is one (1) year. The funding source is Water Fund Operating Budget.

E. Award of Non-Competitive Contract: Automated Meter Reading (AMR) Endpoint Supplies and Services to United Systems of Benton, Kentucky (from Region Supplier) for an estimated annual value of $200,000 based on unit pricing. The contract duration is one (1) year. The funding source is Water Fund Operating Budget.

F. Resolution for forgiveness of Lead Service Line Replacement (LSLR) Program loans in the amount of $5,984.64.

IV. COMMITTEE REPORTS

A. Vouchers in the amount of $7,192,697.88

V. ADJOURNMENT

https://rockfordcityil.iqm2.com/Citizens/FileOpen.aspx?Type=14&ID=3172&Inline=True

 

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS